Current Report No. 82/2018 (2:32 pm)
Topic:
Signing of a significant construction contract for the years 2018-2021 with a net value of PLN 25.97 million for heavy maintenance of national roads administered by the General Directorate of National Roads and Motorways, Bydgoszcz Branch, Districts Nakło, Świecie and Toruń.
Legal basis:
Article 17(1) of the MAR – confidential information
Content of report:
The Management Board of Erbud SA (the “Issuer”) informs that on 17 December 2018, PBDI S.A. from Toruń (a 90% subsidiary of the Issuer), acting in a consortium (the “Contractor”) formed by companies PBDI S.A. (Consortium Leader) and Przedsiębiorstwo Budowy Dróg i Mostów Sp. z o. o. with its registered office in Świecie at 3 Laskowicka Street (Consortium Partner) concluded a significant construction contract on the following terms and conditions:
1. Contract date: 17.12.2018.
2. Customer: Skarb Państwa – Generalna Dyrekcja Dróg Krajowych i Autostrad Oddział w Bydgoszczy [State Treasury – General Directorate for National Roads and Motorways, Bydgoszcz Branch], 85-085 Bydgoszcz, 6 Fordońska Street.
3. Total net contract value: PLN 25,973,675. PBDI will complete 50 percent of this.
4. Contract subject: Heavy maintenance of national roads administered by the General Directorate of National Roads and Motorways, Bydgoszcz Branch, Districts Nakło, Świecie and Toruń, to be performed in 2018-2021.
5. Completion period: until 30 November 2021 or until the maximum remuneration specified in the contract is exhausted.
6. Payment terms: Invoicing at most once a month according to the progress of works; credit period of 30 days.
7. Performance Bond: 5% of the gross remuneration in the form of bank or insurance guarantee valid 30 days from the date of the Final Acceptance Certificate for the last single task order. The Consortium partners provide bonds in proportion to the value of their scope of work.
8. Defects Liability 1.5% of the gross remuneration in the form of bank or insurance guarantee valid 15 days from the expiry date of the warranty period for the last single task order. The Consortium partners provide bonds in proportion to the value of their scope of work.
9. Penalties:
– for withdrawal from the Contract for reasons attributable to the Contractor – 10% of the gross remuneration;
– for delay in the performance of a single task order – 0.4% of the net value of the single task order for each day of delay in it completion,
– for delay in removing defects found during the Final Acceptance for a single task order or during the warranty period due to reasons attributable to the Contractor – PLN 5,000.00 for each day of delay, starting from the date set for the removal of defects.