25.10.2016

Current Report No.79/2016 (2:08 pm)

Topic:
Signing of a significant contract for construction works worth PLN 37,4m – Replacing mills DF90 No. 1 and DF-90 No. 2, incl. retrofitting the sorbent milling lines in Limestone Grinding Facility, Bogatynia
Legal basis:
Article 17 section 1 of the MAR – confidential information

Content of report:     
The Management Board of Erbud S.A. publishes information about entering into a significant contract for construction works by Erbud Industry Sp. z o.o., a company from the Erbud Group, 100% owned by Erbud S.A.. The contract was concluded on the following terms and conditions:

Below is information about the contract conditions:

1. Contract GEK/PMR-ELT/04624/2016 concluded on 25.10.2016.

2. The Investor: PGE Górnictwo i Energetyka Konwencjonalna S.A.; 97-400 Bełchatów, 5 Węglowa St.; NIP: 769-050-24-95.

3. Contract value: PLN 37,446,700 net, of which:
Task No. 1: PLN 19,231,900 net;
Task No. 2: 18,214,800 net.

4. Contract subject: Replacing mills DF90 No. 1 and DF-90 No. 2, incl. retrofitting the sorbent milling lines in Limestone Grinding Facility located in Bogatynia, of which:
Task No. 1: „Replacing the mill DF90 No. 1”;
Task No. 2: „Replacing the mill DF90 No. 2”.

5. Site location: Turów Power Plant, 59-916 Bogatynia, 12 Młodych Energetyków St.

6. Completion period:
Task No. 1: 25.10.2016 – 25.03.2018;
Task No. 2: 25.10.2016 – 25.11.2018.

7. Payment terms: invoicing according to the payment schedule; credit period of 30 days.

8. Performance Bond:
PLN 1,182,761.85, i.e. 5% of the Gross Contract Price – possibility of a bank or insurance guarantee valid until 25.04.2018; and
PLN 1,120,210.20, i.e. 5% of the Gross Contract Price – possibility of a bank or insurance guarantee valid until 25.12.2018.

9. Defects Liability Bond:
PLN 354,828.56, i.e. 5% of the Gross Contract Price – possibility of a bank or insurance guarantee valid until 10.04.2018; and
PLN 336,063.06, i.e. 5% of the Gross Contract Price – possibility of a bank or insurance guarantee valid until 10.12.2020.

10. Other guarantees: none.

11. Penalties:
0.1% of the Net Contract Price for each day of delay;
20% of the Net Contract Price in case of termination of the Contract;
the sum of liquidated damages for any Party, shall not exceed 10% of the Net Contract Price.

12. Note: The contract performed by ERBUD INDUSTRY Spółka z ograniczoną odpowiedzialnością.