06.09.2018

Current Report No. 58/2018 (3:39 pm)

Topic: 

Conclusion of a significant construction contract worth PLN 26 million for the extension of the Solny Hotel in. in Kołobrzeg at 5 Aleksandra Fredry Street, together with site development and technical infrastructure.

Legal basis:

Article 17(1) of the MAR – confidential information

 

Content of report: 

The Management Board of Erbud SA (the “Issuer”) informs that on 6 September 2018 it signed a significant construction contract on the following terms and conditions:

  • Contract: Construction contract for the extension of the Solny Hotel in. in Kołobrzeg at 5 Aleksandra Fredry Street, incl site development and technical infrastructure.
  • Contract date: 06.09.2018.
  • Condition of entry into force of the contract: Conditional contract – the parties shall be entitled to withdraw from the Contract without the right to make any claims in the event of failure to obtain the design change by 2 November 2018.
  • Customer: Solny Investment Sp. z o.o., 78-400 Szczecinek, 21 Królowej Jadwigi Street.
  • Completion period: commencement of works on 02.11.2018; completion – 16 months from the commencement date. Obtaining an occupancy permit within one month from completion date.
  • Volume: 25,147 m3.
  • Area: Usable floor area – 4 468 m2; Gross building area – 6 114 m2.
  • Range of works: construction works including mechanical, electrical and plumbing works, site development and accompanying technical infrastructure.
  • Net contract price: PLN 25,950,000. Advance payment of PLN 4 million net, to be cleared according to the schedule.
  • Site location: Kołobrzeg, 5 Aleksandra Fredry Street.
  • Performance Bond: 5% of the net contract price.
  • Defects Liability Bond: 2.5% of the net contract price.
  • Penalties: 

a)for delay in the completion of Works – 0.06% of net remuneration for each day of delay;

b)for delay in removal of defects found at final acceptance or during the warranty (guarantee) period –  0.02% of net remuneration for each day of delay;

c)for withdrawal from the contract by one of the parties due to the circumstances for which the other party is responsible, except for the right to withdraw as a result of failure to obtain design changes – 10% of net remuneration;

d)Health and Safety penalties – PLN 500 per each case.

Limit of penalties: 10 % of net remuneration.

  • Guarantee and warranty: quality guarantee and warranty for defects

a) 60 months for construction works;

b) 24 months for mechanical, electrical and plumbing works;

c) 24 months for building and installation materials;

d) for plant and equipment according to the manufacturer's warranty but no less than 12 months.

 