25.09.2025

Current report no. 26/2025 (01:34 p.m.)

Subject:
Signing of a Significant Contract amounting to PLN 65 million for subcontracted construction works on the construction of a new SCGT gas cogeneration unit in Łódź.

Legal basis:
Article 17(1) of MAR – confidential information.

Report content:
The Management Board of Erbud SA (the Issuer) hereby announces that on September 25, 2025, it signed a Significant Contract for subcontracted construction works on the construction of a new SCGT gas cogeneration unit in Łódź, under the terms and conditions described below:
1. Date of conclusion: September 25, 2025
2. Investor (full name and registered office): Siemens Energy Sp. z.o.o., Aleja Armii Ludowej 26, 00-609 Warsaw
3. Net Contract value: PLN 65,006,093.88
4. Subject of the Contract: Subcontracting construction works on the construction site of a new SCGT gas cogeneration unit in Łódź
5. Place of Contract performance: EC4 Łódź
6. Completion dates: Completion of works within 20 months from the date of the Contract conclusion.
7. Terms of payment: Do not deviate from market standards.
8. Performance bond (value, term): 10% of the net Remuneration in the form of a bank or insurance guarantee for the duration of the Contract.
9. Retention bond (value, term of validity): 5% of the net Remuneration in the form of a bank or insurance guarantee, reduced during the guarantee period
10. Penalties: Penalties do not differ from market conditions for this type of contract. The total amount of contractual penalties may not exceed 13% of the Remuneration amount.
11. Notes: Construction on the premises of Veolia Energia Łódź, implemented by the Toruń Branch.

Privacy settings

The Administrator may access and use information for the purposes indicated below. You may change the settings according to your preferences or continue using our website if you have no objections.