12.03.2014

Current report No. 8/2014

Topic:
Signing of an annex to the contract dated 23 August 2013 on the execution of complex construction works for the Gawtowice Wind Farm, increasing the contract value by PLN 3.2m
Legal basis:
Article 56 section 1 item 2 of the Act on Public Offering – current and periodic information

Content of report:
The Management Board of ERBUD S.A. informs that on 11 March 2014 the Issuer and the PEP Group – Farma Wiatrowa 1 Spoika z ograniczon4 odpowiedzialnokig with its registered office in Warsaw, 24/26 Krucza St., 02-526 Warsaw (the Investor) signed an annex to the contract of 23 August 2013 (of which the Issuer announced in the Current Report No. 31/2013 of 23 August 2013) changing the scope of work, to execute comprehensive civil engineering works in the field of wind turbines foundations, adaptation of access roads for over dimensional vehicles, upgrading of existing roads, construction of service roads and erecting assembly platforms for the completion of Gawtowice Wind Farm.

By concluding this annex the net contract price increases by PLN 3,264,130.68 (say: three million two hundred sixty-four thousand one hundred thirty, point sxty-eight) and thereby the total value of the contract amounts to 32,975,115.08 net (say: thirty-two million nine hundred seventy-five thousand one hundred fifteen point eight).

All other contract terms and conditions shall remain unchanged.

In the contract, the Issuer is a Partner of a consortium with the company Przedsiqbiorstwo Budownictwa Drogowo-In2ynieryjnego S.A. (Consortium Leader), seated in Tormi , a subsidiary in which the Issuer holds a stake of 94.27 per cent.