07.12.2017

Current Report No.61/2017 (4:10 pm)

Topic:
Signing of a significant contract for construction works worth PLN 57.6 million – Construction as general contractor of a retail and shopping centre in Gliwice on Rybnicka Street, including road system, parking area and associated infrastructure, retaining walls, water meter chamber, pumping station and fire-fighting tanks, pylon and monument sign – 1st stage of completion / phase 1.
Legal basis: Article 17(1) of the MAR – confidential information

Content of report:
The Management Board of Erbud SA (the “Issuer” / the “Company”) informs that it entered today into a construction contract on the following terms and conditions:

1. Contract execution date:  General Contracting Contract of 07.12.2017.

2. Investor: SILESIA OUTLET Sp. z o.o.; 18 Piękna Street, 00-549 Warszawa; NIP: 7010533434.

3. Contract value: PLN 57,560,000.

4. Contract subject: Construction as general contractor of a retail and shopping centre in Gliwice on Rybnicka Street, including road system, parking area and associated infrastructure, retaining walls, water meter chamber, pumping station and fire-fighting tanks, pylon and monument sign – 1st stage of completion / phase 1.

5. Site location: Gliwice.

6. Completion period: from about 29.12.2017 to 29.03.2019.

7. Payment terms – invoicing on monthly basis with a credit period of 30 days.

8. Performance Bond: 10% of net remuneration, i.e. PLN 5,756,000 in the form of a bank guarantee valid until 29.03.2019.

9. Defects Liability Bond: 5% of net remuneration, i.e. PLN 2,878,000 in the form of a bank guarantee for a period of 5 years; 2% of net remuneration, i.e. PLN 1,151,200 in the form of a bank guarantee for the next 5 years.

10.  Other guarantees: none.

11. Penalties:

  • for exceeding the deadline of less than 14 days – 0.1% of net remuneration for each day of delay; for exceeding the deadline of more than 14 days – 0.15% of net remuneration for each day of delay charged from the 15th day;
  • in the case of withdrawal from the contract by any Party – 10% of net remuneration;
  • the limit of contractual penalties for any Party – up to 10% of net remuneration.

12. The contract shall come into force after submitting a written Notice to Proceed by the Investor before 27.12.2017.