Current Report No.62/2017 (11:36 am)
Topic:
The fulfilment of the condition precedent regarding the entry into force of a construction contract – construction of a retail and shopping centre in Gliwice on Rybnicka Street, including road system, parking area and associated infrastructure, retaining walls, water meter chamber, pumping station and fire-fighting tanks, pylon and monument sign (1st stage of completion / phase 1) – receiving the Notice to Proceed.
Legal basis:
Article 17(1) of the MAR – confidential information
Content of report:
On 7 December 2017, the Issuer informed by Current Report No. 61/2017 about signing a significant Contract for construction works. The Contract was a contingent one. The condition for taking effect of the Contract was that the Customer submitted a Notice to Proceed.
On 15 December 2017, the Issuer received the Notice to Proceed, which is tantamount to the entry into force of the Contract.