23.08.2018

Current Report No. 52/2018 (11:11 am)

Topic: 

Conclusion of a construction contract worth PLN 31.6 million to develop the provincial road No. 209 from Suchorze to Bytów, section III.2: Borzytuchom – Bytów.

Legal basis:

Article 17(1) of the MAR – confidential information

 

Content of report: 

The Management Board of Erbud SA (the “Issuer”) informs that on 23 August 2018 PBDI S.A. with its registered office in Toruń (a subsidiary of the Issuer) signed a construction contract under the following terms and conditions.

1. Contract date: 23 August 2018.

2. Customer: Województwo Pomorskie; 88-810 Gdańsk, 21/27 Okopowa Street.

3. Net contract value: PLN 31,613,731.39.

4. Contract subject: Development of the provincial road No. 209 from Suchorze to Bytów, section III.2: Borzytuchom – Bytów. (from 53 + 264 km to 61 + 262 km; length 7 998 km),

5. Completion period: deadline on 22 September 2019.

6. Payment terms: monthly invoicing payable within 30 days.

7. Performance Bond: 10% of gross remuneration, i.e. PLN 3,888,488.96 in the form of a bank or insurance guarantee valid until 11 October 2019.

8.  Defects Liability Bond: 3% of gross remuneration, i.e. PLN 1,166,546.69 in the form of a bank or insurance guarantee provided for the period from 12 October 2019 to 25 September 2027.

9. Other guarantees: None.

10. Penalties: for delay in delivery of works – 0.01% of net remuneration for each day of delay; for withdrawal from the contract for reasons attributable to the Contractor – 10% of net remuneration.

 