Current Report No. 31/2019 (2:34 pm)
Topic:
Fulfilment of conditions precedent of a significant contract of 12.06.2018 for the detailed design development, construction and commissioning of the 101.25 MW Potęgowo-Wschód Wind Farm.
Legal basis:
Article 17(1) of the MAR – confidential information
Content of report:
With reference to Current Reports Nos. 45/2018 of 16 August, 46/2018 of 16 August 2018, 9/2019 of 4 February 2019 and 22/2019 of 10 May 2019, the Management Board of ERBUD S.A. with its registered office in Warsaw (the "Issuer") announces that all conditions precedent determining the Issuer's accession to the performance of the second stage of the construction contract dated 12 June 2018 for the development of detailed design, construction and commissioning of the Potęgowo-Wschód Wind Farm with a capacity of 101.25 MW, has been fulfilled.
Therefore, the Management Board of Erbud S.A. informs that the execution of the second stage of the contract referred to above comes into force.