Current Report No. 57/2019 (12:44 pm)
Topic:
Fulfilment of the condition precedent to the Agreement for construction works connected with the construction of the Wind Power Facility Szymankowo.
Legal basis:
Article 17(1) MAR – confidential information.
Content of the Report:
Referring to the Report No. 56/2019 the Management Board of ERBUD S.A. (Issuer) informs that on 8 November 2019 the company PBDI S.A from Toruń (90%-subsidiary of the Issuer) received instructions from the Investor (Polenergia Farma Wiatrowa Szymankowo Sp. z o. o.) to commence works at the construction of the Wind Power Facility Szymankowo.